Chimney removal in Bilthoven: before and during
See how Sloop Concurrent removed a chimney from a home in Bilthoven. Three photographs and the sequence of the two working days.



How were the two working days used?
The first day was for erecting the scaffold. On the second day the team removed the chimney and cleared the rubble. Sloop Concurrent describes the chimney at this property as non-load-bearing.
What these photographs show
These are before and work-in-progress photographs. They do not show the finished roof opening. Each work stage is identified so you can understand the project. Timing and approach for another property are assessed separately.
Source: Sloop Concurrent project archive ↗
For your own schedule, consider whether the scaffold will fit on your land and whether rubble can leave by the same route. If the chimney carries a load at your property, its support also needs assessment.